CIGRE Paris Session 2026 title slide for From Administrative Curtailment to Dispatchable Load.

Submission files

2 files · PDF abstract + PowerPoint slides

Knowledge Hub/Resource

From Administrative Curtailment to Dispatchable Load: The PCLR Architecture

A CIGRE Session 2026 contribution explaining how ERCOT's Provisional Controllable Load Resource architecture turns conditional large-load consumption into a visible, locational, dispatchable market resource.

2 files · PDF abstract + PowerPoint slides

Submission files

Abstract and presentation deck

View the available publication materials online or download the original submission files.

Research note

Curated

Updated Aug 13, 2026 · Arushi Sharma Frank · CIGRE Paris Session 2026 · Study Committee C5

01

Separates the grid-backed firm planning floor, LPC, from the approved upper operating level, MPC.

02

Places provisional consumption inside security-constrained economic dispatch through telemetry, bids, operating limits, ramp capability, and locational shift factors.

03

Includes the one-page CIGRE abstract and the four-slide presentation deck in their original submitted formats.